8 underway, 6 planned, 6 done

Makes the town's drinking water. Shared with New Tecumseth. The biggest project in the Town's history.
Where it stands: Under construction since July 2024. New supply expected late 2029; fully complete in 2032.
Council passed an Interim Control By‑law (2021‑024), pausing some new development over water capacity.
Source: Staff Report IN2026-03
Most new building now needs the Town to confirm water and sewer capacity first (By‑law 2022‑007).
Source: Staff Report IN2026-03
Bids came in. Lowest was $212M for construction. Total now about $270M, and two years later.
Source: Engage Collingwood
Construction began.
Source: Engage Collingwood
Capacity update: about 892 m³ a day of uncommitted water capacity (about 670 homes) as of Dec 31, 2025, with a 5% safety factor.
Source: Staff Report IN2026-03
Council approved new development charges so new homes pay toward the plant (RES‑158‑2026).
Source: Council minutes, 20 Apr 2026
Town update: total about $270M, with $150M in provincial funding. Extra 5,000 m³ a day online since late July 2026. On schedule and on budget.
Source: Town news, Aug 13, 2026
Every step, cost and decision for the biggest projects.
See how costs changed over time in Project Decision Timelines.
Every project comes from the Town: its news releases, its Construction Projects page, Engage Collingwood project pages, and Council agendas and minutes. Each row links to its sources.
We only show a finish date or a reason for a delay when the Town has published one. When it hasn't, the row says so.
20 projects listed. Dates can change, so check the source before you plan around one.
Questions? Call the Town at 705-445-1030 or email service@collingwood.ca.
Source: Town of Collingwood, Construction Projects