| Who | For what | Value | How hired |
|---|---|---|---|
AECOM, with Ainley Group Verified | Phase 1 design and contract administration | Not published yet | Not published yet |
"Not published yet" means we could not find the figure in a public Town source.

Council passed By-law 2021-024, 6–3, pausing some new development over water capacity.
Official sourceLow bid $212M for construction. Total cost estimated at about $270M, with the schedule about two years longer.
Official sourceConstruction started in July 2024.
Official source$270M total, $70M in grants at the time (provincial funding is now $150M). New Tecumseth pays 63%, Collingwood 37%.
Official sourceAn extra 5,000 m³ a day came online at the end of July 2026. Total about $270M, with $150M in provincial funding. The Town says the project is on schedule and on budget.
Official sourceExpected in late 2029. The expanded plant should be fully complete in 2032.
Official sourceLatest decision
Council approved the 2026 amended development charge study for the plant and the lower charges in it. Council confirmed it on May 4, 2026 (RES-180-2026).
No votes against. No vote shown: Yvonne Hamlin.
RES-158Town voting record 2026, pp. 233-235 (Town of Collingwood, opens in a new tab)
Council–Committee of the Whole meeting
Earlier
Noting a budgeted cost of $270,000,000 and a projected finish in January 2032, Council asked staff for quarterly updates on the timeline, costs and risks, and for Joint Water Committee minutes within 4 weeks of approval.
No votes against. No vote shown: Ian MacCulloch.
RES-073Town voting record 2026, pp. 107-115 (Town of Collingwood, opens in a new tab)
Council–Committee of the Whole meeting
Council passed By-law 2025-024, which amends the water treatment plant development charges.
No votes against.
RES-150Town voting record 2025, pp. 211-212 (Town of Collingwood, opens in a new tab)
Council–Committee of the Whole meeting
From Council minutes and budgets (October 2022 to October 2026). Member votes come from the Town's voting record, which starts in 2025.
Council passed By-law 2021-024, 6–3, pausing some new development over water capacity.
Official sourceLow bid $212M for construction. Total cost estimated at about $270M, with the schedule about two years longer.
Official sourceConstruction started in July 2024.
Official source$270M total, $70M in grants at the time (provincial funding is now $150M). New Tecumseth pays 63%, Collingwood 37%.
Official sourceAn extra 5,000 m³ a day came online at the end of July 2026. Total about $270M, with $150M in provincial funding. The Town says the project is on schedule and on budget.
Official sourceExpected in late 2029. The expanded plant should be fully complete in 2032.
Official sourceInterim control by-law exemptions
The Town granted 134 exemptions, allowing 1,225 building permits while the by-law was in effect; 2021 saw the most building permits in the Town's history.
Total project cost
About $270 million, with $150 million in provincial funding and the remainder shared with the Town of New Tecumseth.
Cost split
About 37 percent Collingwood and 63 percent New Tecumseth (applies to the new interim capacity and to remaining costs).
Completion
Additional water supply expected late 2029; construction fully complete in 2032.
Servicing Capacity Allocation Policy
Replaced the ICBL; a merit-based points system (out of 95 points) for allocating water and wastewater capacity; reserve drinking water capacity was 1,837 cubic metres per day as of January 1, 2023.
Apr 26, 2021
Council votes, not unanimously and after a seven-hour meeting, for Interim Control By-law 2021-024, a pause on new development to protect the limited remaining supply of unallocated drinking water.
CollingwoodToday(opens in a new tab)2022
Expansion estimated at about $121 million when Collingwood and New Tecumseth worked out a new water agreement.
CollingwoodToday(opens in a new tab)Feb 21, 2023
RES-063-2023: Council asks for a joint letter with New Tecumseth requesting provincial funding for the plant expansion.
Town of Collingwood, p. 10(opens in a new tab)Jul 19, 2023
Interim Control By-law no longer in effect after the final appeal of Zoning By-law Amendment 2022-007 was withdrawn.
Town of Collingwood(opens in a new tab)Sep 2023
Bids received; unofficial low bid $212 million for construction; total project estimated around $270 million, with the timeline extended about two years.
Town of Collingwood(opens in a new tab)Jun 19, 2024
'Celebration of Water' groundbreaking event at the plant.
Town of Collingwood(opens in a new tab)Sep 26, 2024
Ontario announces $69,999,999.58 from the Housing-Enabling Water Systems Fund for the Raymond A. Barker plant expansion.
Ontario government announcement via MPP Brian …(opens in a new tab)Apr 2026
Council told the province will provide an additional $80 million, bringing provincial funding to $150 million.
CollingwoodToday(opens in a new tab)Jul 2026
Interim capacity of an additional 5,000 cubic metres per day comes online.
Town of Collingwood news(opens in a new tab)Why the freeze happened: by 2021 the Raymond A. Barker Water Treatment Plant was approaching its maximum capacity. Collingwood also supplies treated water to New Tecumseth by pipeline. In April 2021 Council passed an interim control by-law at staff's urging to protect the limited remaining unallocated water. Building continued through exemptions. The by-law was lifted on July 19, 2023 and replaced by a Servicing Capacity Allocation Policy. (Sources: CollingwoodToday, 'Collingwood lifts development moratorium' (July 2023); Town of Collingwood, Engage Collingwood: Interim Control By-law (ICBL) page; CollingwoodToday, 'Collingwood water plant costs, delay put New Tec housing targets out of reach' (Sept 2023))
CollingwoodToday(opens in a new tab)The expansion: the 2023 bids more than doubled the March 2022 estimate, according to a joint statement from Mayor Hamlin and New Tecumseth Mayor Norcross. Provincial funding of $70 million (2024) and a further $80 million (2026) brought provincial support to $150 million. Construction started in July 2024, and the Town reports the project is on schedule and on budget. (Sources: Town of Collingwood, Engage Collingwood: Water Treatment Plant Expansion; Ontario government announcement via MPP Brian Saunderson's office, 'Ontario Helping Build More Homes in the Town of Collingwood & the Town of New Tecumseth' (Sept 26, 2024); CollingwoodToday, 'Still on budget and on time, Collingwood's water treatment plant expansion continues' (Aug 2026); Town of Collingwood news, 'Town Celebrates Two Years of Progress on Water Treatment Plant Expansion' (Aug 13, 2026))
Town of Collingwood(opens in a new tab)The joint statement on the 2023 bids is posted on the Town's WTP Engage page without a date in the captured text; CollingwoodToday's late-September 2023 coverage places the bids in September 2023 (bids valid until Nov 11).
Town of Collingwood(opens in a new tab)