Eddie Bush arena
Opened December 16, 1948 as the Collingwood Community Arena on Hurontario Street: a $194,000, 17,000-square-foot arena with artificial ice and capacity for 3,000 people. In the 1947 election, ratepayers voted 704 to 424 in favour of building it.
Sprung cost in the August 2012 staff report
Total cost of the two buildings $10,617,000; accessory costs $316,000; site servicing $700,000; total (less taxes) $11,633,000, with $8,000,000 shown from the Collus PowerStream partnership.
MURF site
725 Tenth Line: 37-acre property with about 34 buildable acres; conditions of sale expected to be completed by the end of 2026; purchase price to be disclosed once the sale closes; an alternative site has been identified if conditions are not met.
MURF size requirement
The Joint MURF Feasibility Assessment set a requirement for a site of at least 20 acres for a building of up to 245,000 square feet plus parking and site infrastructure.
2003 cost estimate
The October 2003 feasibility study estimated construction at $18,864,513 plus $4,656,361 in development costs for a facility of about 115,000 sq ft with an ice pad, pools and other amenities, and a first-year operating subsidy of about $400,000.
2003 funding plan
The October 16, 2003 motion proposed $3.3 million from land sales, $2 million in debt and a $2.54 million SuperBuild grant.
2012 cost concern
The August 27, 2012 options presentation listed 'Concern with $35 million cost' for the multi-use facility.
Centennial Pool & Single-Pad Arena Options pre…, p. 9(opens in a new tab)MURFA cost benchmark
The July 2025 MURFA report did not estimate a cost for a Collingwood building. It cites the Altus Canada 2025 Costing Guide range of $670 to $1,180 per square foot in hard construction costs for multi-recreation facilities, plus soft costs.
Joint Multi-Use Recreation Feasibility Assessm…, p. 95(opens in a new tab)Land purchase
Staff report PRC2026-09 says a conditional offer for 725 Tenth Line was signed on August 5, 2026. The property is being sold through a court-appointed sales officer, so court approval and a vesting order are needed, expected in Q4 2026. The purchase is funded from the MURF Reserve Fund, Recreation Development Charges and, if needed, internal borrowing.
Town of Collingwood Staff Report PRC2026-09(opens in a new tab)Dec 16, 1948
Collingwood Community Arena (later Eddie Bush Memorial Arena) opens downtown.
CollingwoodToday(opens in a new tab)Oct 16, 2003
Council passes a motion recommending that the incoming Council build a Multi-Use Recreation Facility (MURF), funded with $3.3 million from land sales, $2 million in debt and a $2.54 million SuperBuild grant, at one of four sites including Tenth Line next to Fisher Field.
Collingwood Judicial Inquiry Report, p. 20(opens in a new tab)Oct 22, 2003
Final report of the Collingwood Multiple-Use Recreation Facility needs and feasibility study: about 115,000 sq ft, estimated construction cost $18,864,513 plus $4,656,361 in development costs; top-ranked site at Tenth Line and Sixth Street, next to Fisher Field.
Collingwood Multiple-Use Recreation Facility, p. 6(opens in a new tab)Feb 5, 2004
The newly elected Council first votes against applying for the grant, then reverses itself at the same meeting and votes to pursue an application to build the MURF at Fisher Field.
Collingwood Judicial Inquiry Report, p. 21(opens in a new tab)Feb 23, 2004
Council reverses that decision, effectively turning down the SuperBuild grant funding the Town would otherwise have qualified to receive.
Collingwood Judicial Inquiry Report, p. 21(opens in a new tab)Jan 2008
The Leisure Services Master Plan records that the facilities recommended by the earlier MURF feasibility study were not developed.
Town of Collingwood Leisure Services Master Plan, p. 14(opens in a new tab)2011
The Town begins exploring a new multi-use recreational facility in Central Park; a volunteer steering committee develops proposals in 2011 and 2012.
Collingwood Judicial Inquiry Report, p. 22(opens in a new tab)Mar 2012
Volunteer steering committee recommends a multi-use recreational facility; Council later balks at the estimated $35 million cost.
Collingwood Judicial Inquiry Report, p. 23(opens in a new tab)Aug 27, 2012
Council votes to purchase and construct two Sprung fabric structures (arena and pool cover) instead of one large multi-use facility.
Collingwood Judicial Inquiry Report, p. 25(opens in a new tab)Aug 27, 2013
Renovated Centennial Pool officially opens to the public.
Collingwood Judicial Inquiry Report, p. 320(opens in a new tab)Oct 14, 2013
Central Park Arena has a 'soft opening'.
Collingwood Judicial Inquiry Report, p. 320(opens in a new tab)2019
The Parks, Recreation and Culture Master Plan recommends reviewing the feasibility of a MURF, possibly as a regional facility.
Town of The Blue Mountains Staff Report CS.25.…, p. 1(opens in a new tab)Jul 31, 2023
Collingwood Council directs staff to work with The Blue Mountains on a Joint Multi-Use Recreation Feasibility Assessment (MURFA).
Town of The Blue Mountains(opens in a new tab)Aug 28, 2023
The Blue Mountains Council approves the joint study; each town contributes $100,000 ($200,000 total).
Town of The Blue Mountains(opens in a new tab)Jul 29, 2024
RES-399-2024: Council asks staff for terms of reference for a MURF steering committee.
Town of Collingwood, p. 7(opens in a new tab)Oct 30, 2024
Consultants report MURFA public input to a joint special meeting: 3,370 survey responses and 151 youth responses, with a 5:1 preference for a multi-use facility over single-use facilities.
Colliers Project Leaders, p. 11(opens in a new tab)Nov 13, 2024
RES-103-2024: motion to add $375,000 for MURF and Arts Centre next steps to the draft 2025 budget DEFEATED.
Town of Collingwood, p. 6(opens in a new tab)Dec 16, 2024
RES-201-2024: motion to approve $300,000 from reserves toward MURF and Arts Centre DEFEATED; RES-207-2024 adopts the MURF Steering Committee and its terms of reference.
Town of Collingwood, p. 12(opens in a new tab)Mar 17, 2025
RES-124-2025: public and local sports representatives appointed to the MURF Steering Committee.
Town of Collingwood, p. 8(opens in a new tab)Jul 16, 2025
Colliers Project Leaders presents the final Joint Multi-Use Recreation Feasibility Assessment (MURFA) to a joint special meeting of Collingwood and The Blue Mountains councils. It recommends exploring a joint recreation and library facility and preparing a detailed business case.
Joint Multi-Use Recreation Feasibility Assessm…, p. 4(opens in a new tab)Oct 6, 2025
RES-444-2025 approves committee recommendations including PRC2025-05 MURF Feasibility Assessment Next Steps (amended): a location assessment, with up to $10,000 from the MURF Reserve.
Town of Collingwood, p. 5(opens in a new tab)Oct 20, 2025
The Town invites landowners to offer sites, seeking about 20 acres for a MURF.
Town of Collingwood news(opens in a new tab)Dec 1, 2025
The Blue Mountains Council votes to pursue a partnership approach on a multi-use recreation facility.
Town of The Blue Mountains(opens in a new tab)Dec 1, 2025
RES-536-2025: $50,000 of the Town's MAT share directed to the MURF Reserve Fund and $50,000 to the Arts Centre Reserve Fund in the 2026 budget.
Town of Collingwood, p. 14(opens in a new tab)Dec 8, 2025
Council receives the site assessment results in closed session and directs staff to investigate further.
Town of Collingwood(opens in a new tab)Mar 30, 2026
Council approves up to $15,000 from the MURF Reserve for environmental studies of shortlisted sites (PRC2026-01).
Town of Collingwood(opens in a new tab)May 11, 2026
RES-204-2026: up to $10,000 authorized for an appraisal of a shortlisted MURF property.
Town of Collingwood, p. 2(opens in a new tab)Jun 22, 2026
In closed session, Council directs staff to negotiate for two properties, with 725 Tenth Line preferred.
Town of Collingwood Staff Report PRC2026-09(opens in a new tab)Aug 10, 2026
RES-327/328-2026: By-law 2026-060 enacted to acquire 725 Tenth Line for a MURF and/or other strategic opportunities.
Town of Collingwood, p. 8(opens in a new tab)Collingwood has been trying to build a multi-use recreation facility for more than 20 years. The Judicial Inquiry report says that throughout the 2000s, Council and staff looked at how to build and fund new recreation facilities, without success. A 2003 feasibility study proposed a facility of about 115,000 sq ft next to Fisher Field. In February 2004 the newly elected Council voted to pursue it and, 18 days later, reversed that decision, effectively turning down SuperBuild grant funding. (Sources: Collingwood Judicial Inquiry Report, Vol. III: Part Two, The Arena and the Pool (Nov 2, 2020); Collingwood Multiple-Use Recreation Facility: Recreation Needs and Project Feasibility Study, Final Report (Oct 22, 2003), Collingwood Judicial Inquiry document archive)
Collingwood Judicial Inquiry Report(opens in a new tab)In 2011 and 2012 the Town explored a multi-use facility in Central Park. Council balked at the estimated $35 million cost, and on August 27, 2012 it chose the two Sprung fabric buildings, the Central Park Arena and the Centennial Pool cover, which opened in 2013. The Inquiry report's title for Part Two is 'The Arena and the Pool: The Real Cost of Sole Sourcing'. (Sources: Collingwood Judicial Inquiry Report, Vol. I: Executive Summary and Recommendations (Nov 2, 2020); Collingwood Judicial Inquiry Report, Vol. III: Part Two, The Arena and the Pool (Nov 2, 2020))
Collingwood Judicial Inquiry Report(opens in a new tab)The current MURF process began with a joint feasibility assessment with the Town of The Blue Mountains. Council created a steering committee in December 2024 and in August 2026 enacted a by-law to buy 725 Tenth Line, near Fisher Fields, as the preferred site. The amenities have not been finalized, and the location of a future Arts Centre is being assessed separately. (Sources: Town of Collingwood, Engage Collingwood: Joint Multi-Use Recreation Feasibility Assessment (MURFA); Town of Collingwood news, 'Future Recreation Facility Moves Forward with Site Approval' (Aug 11, 2026))
Town of Collingwood(opens in a new tab)Some accounts put the start around 1998 to 2001. In his closing submission to the Judicial Inquiry, Paul Bonwick stated that Council set up a MURF steering committee in about 1998-99, approved a MURF of about $24 million at Fisher Field, and rescinded that approval in 2001, with about $9 million in grant approvals returned. The submission itself says he may have some dates wrong. It is one participant's account; the Inquiry report makes no such finding, and no Council record of it was found for this file.
Closing submissions of Paul Bonwick to the Col…(opens in a new tab)News accounts of the money given back differ from the Inquiry report. Simcoe.com reported that about $8 million in provincial funding was returned after a 2005 vote; the Inquiry report describes the decision as February 23, 2004 and names a $2.54 million SuperBuild grant.
Simcoe.com(opens in a new tab)The date of the location-assessment direction differs by source: The Blue Mountains staff report CS.25.046 gives September 16, 2025; Collingwood's minutes show a Committee of the Whole recommendation on September 15, 2025, approved by Council on October 6, 2025 (RES-444-2025).
Town of The Blue Mountains Staff Report CS.25.…(opens in a new tab)The Blue Mountains voted on December 1, 2025 to pursue a partnership approach, but Simcoe.com reported in August 2026 that joint plans with The Blue Mountains had not gone ahead. The 725 Tenth Line purchase is Collingwood's own.
Town of The Blue Mountains(opens in a new tab)